Our New Offices

The New Big Radio Spain and Quesada Tech Offices

For the last 10 months we have been working on expanding the Big Radio and Quesada Tech Offices, to say that it has been a mammoth task is an understatement with first locating a suitable building and then drawing up the plans to maximise the usable space.

Once the building work started we hit all the usual snags, electrics, plumbing paperwork etc. so here is a rundown of the progress from start to its current state.

We are looking forward to our opening day very soon and will announce it on here , our social media pages and on the radio, and we would like to invite everyone to come, look around and even sit in the big chair for a go at being a presenter

At Big Radio Spain we are committed to being environmentally friendly and working with our partners Solar Costa Blanca, the studios are now run on 100% renewable energy, click the clink below to see how much energy we are producing and the excess is fed back in to the national grid

Big Radio Solar

1st of September 2024 Our First Viewing

16th September 2024, Planning the space

20th November 2024, Demolition Begins

27th November 2024, Demolition Complete, new door fitted to the side entrance and wall frames starting construction

3rd December 2024, Walls going up, ceilings being refurbished and equipment room constructed

5th Jan 2025, Electrics and network cables being run, Manager office walls in place and Production room walls being fitted

23rd Jan 2025, Internal boarding, Network installation, front wall for production built and studio windows being prepped for cutting out

29th Jan External sign boards fitted, door frames going in and prepping manager office for painting

21st Feb 2025 Doors being hung, solar panel fitting begins and first set of disabled ramp footings laid

6th to 26th March 2025, clearing rooms to prep for carpetting, and flooring, front shop wall being built

2nd April 2025, Disabled ramp and steps construction begins

16th May 2025 Ramp constructed and rendering begins

28th May 2025, Ramp and terrace tiling, studio 2 carpeting

7th June 2025, Studio 2 carpet tiles laid and skirting fitted, studio 1 carpeting and outside steps tiled

18th June Aircons fitted, laminate flooring going down

27th June, Units being fitted to manager office and kitchen area and first signs going up

2nd to 12th July 2025, Signboards up, studios being kitted out with lighting and furniture, exterior painting done and railings finished

30th July 2025, Production Studio carpetting, shop flooring laid, solar signs fitted and skirting finished

8th to 25th August 2025, Final Kitting of studios, managers office,production and shop

Walk through video of where we are now